Estimating & bidding: Alaska Contractor Business & Law Practice Questions

Takeoffs, unit costs, overhead and profit, markup vs. margin, bid documents, addenda, alternates, bid mistakes and bid bonds.
Often missed
Question 1
What is a quantity takeoff?
Question 2
Which of these is a direct job cost?
Question 3
A job trailer, temporary toilets and a site superintendent used only on one project are best classified as what?
Question 4
A contractor's job cost is $80,000 and it adds a 15% markup on cost. What is the bid price?
Question 5
A contractor wants a 20% gross margin on the selling price. What markup on cost produces that margin?
Question 6
A job sells for $250,000 and costs $210,000. What is the gross margin as a percentage of the selling price?
Question 7
A slab is 30 ft by 40 ft and 4 in thick. About how many cubic yards of concrete does it need, before waste?
Question 8
A takeoff shows 2,000 square feet of drywall and the estimator uses a 10% waste factor. How much should be priced?
Question 9
What does labor burden add to an employee's base wage in an estimate?
Question 10
A crew will need 120 labor hours at $30 per hour, and labor burden is 35% of wages. What is the estimated labor cost?
Question 11
A finisher installs 40 square feet of tile per hour. How many hours are needed for 1,000 square feet?
Question 12
What is an addendum during bidding?
Question 13
A bid form asks for a base bid plus a price to upgrade the flooring. What is that upgrade price called?
Question 14
The specifications carry a $5,000 allowance for light fixtures the owner has not chosen. The owner picks fixtures costing $6,200. What usually happens?
Question 15
What is a unit-price bid?

Ready for the real exam?

Get every question, unlimited calculation practice and timed mock exams in the app.
Coming soon
Download on the App Store
Coming soon
Get it on Google Play
Not affiliated with any state agency, TDLR, PSI, NFPA, EPA or CSLB. NEC® and National Electrical Code® are registered trademarks of NFPA.
Practice questions are written in our own words and cite code sections by number. Always study from your own copy of the code and the official candidate bulletin.
PrivacyTerms
© 2026 Trovyn Tech LLC