What is the correct order for making a PVC solvent-cement joint?
Correct answer: Cut, deburr, clean, dry fit, prime, cement, join with a quarter turn, hold
Trade practice (PVC solvent joint)
Preparation comes first (square cut, deburr and chamfer, clean, dry fit), then primer and cement while the primer is still wet, then a quarter turn and a hold so the pipe does not push back out.
Question 2
Why is a slight bevel (chamfer) put on the outside edge of a PVC pipe end before cementing?
Correct answer: So cement is not scraped off going in
Trade practice (PVC solvent joint)
A square sharp edge wipes the cement out of the socket as the pipe goes in; a small chamfer keeps the cement in the joint.
Question 3
After pushing a cemented PVC pipe into its fitting, why give it a quarter turn and hold it?
Correct answer: To spread the cement and stop push-back
Trade practice (PVC solvent joint)
The quarter turn spreads the cement around the joint; holding it for about 30 seconds keeps the tapered socket from pushing the pipe back out.
Question 4
How long must a new PVC DWV joint cure before the system is tested?
Correct answer: Per the cement maker's chart
Trade practice (PVC solvent joint)
Cure time depends on pipe size, temperature and humidity; follow the cement manufacturer's cure chart before pressure or water testing.
Question 5
When soldering a copper joint, where should the torch flame be aimed?
Correct answer: At the fitting, so solder flows toward the heat
Trade practice (copper solder joint)
Heating the fitting lets capillary action pull molten solder into the joint; solder should melt on contact with the hot joint, not in the flame.
Question 6
Why must the inside burr be reamed from a cut copper tube?
Correct answer: The burr causes erosion and restricts flow
Trade practice (copper solder joint)
A tube cutter rolls a burr inward. Left in place, it makes turbulence that wears through the tube (erosion corrosion) and reduces flow.
Question 7
A copper joint was overheated until the flux turned black. What is the likely result?
Correct answer: The solder will not flow in and it may leak
Trade practice (copper solder joint)
Burned flux and oxidized copper keep solder from wetting the surfaces. The joint should be taken apart, cleaned and redone.
Question 8
When brazing copper-to-copper joints with a copper-phosphorus (BCuP) filler, what is true about flux?
Correct answer: It is usually not needed on copper
Trade practice (brazing)
Copper-phosphorus alloys are self-fluxing on copper; flux is needed when brazing copper to brass or bronze. Medical gas brazing also uses a nitrogen purge.
Question 9
After cutting and threading steel pipe, what must be done to the pipe end before assembly?
Correct answer: Ream the inside burr and clean the threads
Trade practice (threaded steel joint)
Reaming removes the burr that would restrict flow and catch debris; threads are cleaned of chips and oil before joint compound goes on the male threads.
Question 10
When threading steel pipe with a die, how far should the threads be cut?
Correct answer: Until the pipe end is about flush with the die
Trade practice (threaded steel joint)
Standard pipe threads are tapered; cutting until the pipe end is about flush with the die gives the right length. Over-threading leaves weak, exposed threads.
Question 11
What is the correct way to install a no-hub coupling on cast iron soil pipe?
Correct answer: Gasket on, ends to the center stop, shield over, torque to spec
Trade practice (no-hub cast iron joint)
Both pipe ends must butt against the gasket's center stop; the stainless shield goes over the gasket and the bands are tightened to the maker's torque, alternating sides.
Question 12
What tool is usually used to cut cast iron soil pipe on the job?
Correct answer: A soil pipe snap cutter
Trade practice (no-hub cast iron joint)
A chain-type snap cutter scores and breaks cast iron cleanly and square; abrasive saws are also used.
Question 13
Calculation
Use the 45-degree constant 1.414. A stack must jog 16 inches. What is the center-to-center travel between the two 45-degree fittings?
Correct answer: 22.62 inches
Trade practice (offsets)
Multiply the offset by 1.414 for 45-degree fittings.
Worked solution
1
Formula
Travel = offset × 1.414
2
Values
Travel = 16 × 1.414 = 22.624
3
Result
Travel = 22.62 inches
Question 14
In a 45-degree offset, how does the run (setback) compare with the offset?
Correct answer: They are equal
Trade practice (offsets)
A 45-degree offset makes an isosceles right triangle: the run equals the offset, and the travel is 1.414 times either.
Question 15
Calculation
Use the 22-1/2-degree constant 2.613. A drain must offset 10 inches with 22-1/2-degree fittings. What is the travel?
Correct answer: 26.13 inches
Trade practice (offsets)
Flatter fittings need a longer travel: 2.613 for 22-1/2 degrees versus 1.414 for 45 degrees.
Get every question, unlimited calculation practice and timed mock exams in the app.
Coming soon
Download on the App Store
Coming soon
Get it on Google Play
Not affiliated with any state agency, TDLR, PSI, NFPA, EPA or CSLB. NEC® and National Electrical Code® are registered trademarks of NFPA.
Practice questions are written in our own words and cite code sections by number. Always study from your own copy of the code and the official candidate bulletin.