General requirements: NASCLA Commercial General Building Practice Questions

Project management and scheduling, submittals and RFIs, quality control and special inspections, temporary facilities, building-code basics (occupancy, construction type, fire protection, means of egress, accessibility) and OSHA 1926 safety: fall protection, ladders, scaffolds, cranes, fire prevention and health hazards.
Often missed
Question 1
In a critical path method (CPM) schedule, what is the critical path?
Question 2
Calculation
An activity has an early start of day 12, a late start of day 18 and a duration of 5 days. What is its total float?
Question 3
Calculation
Activity A (4 days) and activity B (6 days) both start on day 0. Activity C (3 days) can start only when both A and B are finished. In a forward pass, what is C's early finish?
Question 4
What is free float?
Question 5
Which schedule format shows activities as horizontal bars on a calendar but usually does not show the logic links between them?
Question 6
In a precedence diagram, a finish-to-start relationship with a 2-day lag between "pour slab" and "strip forms" means what?
Question 7
The project manager adds a second crew to a critical activity to shorten the schedule, accepting a higher cost. What is this called?
Question 8
What is the main purpose of shop drawings?
Question 9
Before sending a subcontractor's submittal to the architect, what should the general contractor do?
Question 10
A superintendent finds that two drawings show different ceiling heights for the same room. What is the proper document to resolve it?
Question 11
Why should the superintendent keep a daily log on every workday?
Question 12
What is a punch list?
Question 13
Which group of documents is normally turned over to the owner at project closeout?
Question 14
What is building commissioning?
Question 15
Under the IBC, who generally employs the special inspector for work that needs special inspection?

Ready for the real exam?

Get every question, unlimited calculation practice and timed mock exams in the app.
Coming soon
Download on the App Store
Coming soon
Get it on Google Play
Not affiliated with any state agency, TDLR, PSI, NFPA, EPA or CSLB. NEC® and National Electrical Code® are registered trademarks of NFPA.
Practice questions are written in our own words and cite code sections by number. Always study from your own copy of the code and the official candidate bulletin.
PrivacyTerms
© 2026 Trovyn Tech LLC