Masonry: NASCLA Commercial General Building Practice Questions

Brick and concrete block units, mortar types and grout, reinforcement and ties, bonds and joints, cold and hot weather, wall bracing and the limited access zone, and block, brick and mortar counts.
Question 1
What are the actual dimensions of a standard 8 x 8 x 16 concrete masonry unit (CMU)?
Question 2
Calculation
Using 1.125 standard 8 x 16 blocks per square foot of wall (given), how many blocks are needed for a wall 80 ft long and 12 ft high with no openings, before waste?
Question 3
Calculation
A CMU wall is 60 ft long and 10 ft high and has two openings of 3 ft by 7 ft and one of 6 ft by 4 ft. Using 1.125 blocks per square foot (given), how many blocks are needed before waste?
Question 4
Calculation
Modular brick runs about 6.75 bricks per square foot of wall (given). How many bricks are needed for 1,200 sq ft of veneer, adding 5% waste?
Question 5
Which mortar type has the highest compressive strength and is often used below grade and for foundations?
Question 6
Which mortar type is commonly used for general above-grade exterior walls and veneer?
Question 7
How does masonry grout differ from mortar?
Question 8
When grout is placed in lifts higher than about 5 ft 4 in, what must usually be provided at the bottom of the cells?
Question 9
Horizontal joint reinforcement in a CMU wall is commonly placed at what vertical spacing?
Question 10
In a brick veneer wall, what are wall ties used for?
Question 11
Why are weep holes placed at the base of a masonry veneer wall just above the flashing?
Question 12
OSHA requires a limited access zone whenever a masonry wall is being built. How wide must that zone be?
Question 13
Calculation
A masonry wall is being built to a height of 14 ft. How wide must the limited access zone be?
Question 14
Under OSHA, masonry walls over what height must be adequately braced until permanent supporting elements are in place?
Question 15
In cold-weather masonry construction, what is a key precaution?

Ready for the real exam?

Get every question, unlimited calculation practice and timed mock exams in the app.
Coming soon
Download on the App Store
Coming soon
Get it on Google Play
Not affiliated with any state agency, TDLR, PSI, NFPA, EPA or CSLB. NEC® and National Electrical Code® are registered trademarks of NFPA.
Practice questions are written in our own words and cite code sections by number. Always study from your own copy of the code and the official candidate bulletin.
PrivacyTerms
© 2026 Trovyn Tech LLC